Search

Ngatai / Bureta Road

Whakapaitanga ki te kōpae ara ki Bureta me Ngātai

Ngatai/Bureta Road intersection safety improvements

The Ngatai/Bureta Road intersection is getting a much-needed safety upgrade.

Construction update

The next stage of works will shift to the southern side of the intersection from Tuesday, 7 July. This will mean the northern side of Bureta Road near the train tracks will re-open.

From Tuesday, 7 July a 24/7 road closure will be in place on the southern side of Bureta Road (outside the Bureta shops) for approximately six weeks, weather permitting. Ngatai Road will remain open with a 30km/h speed limit through the work site.

There will be no access from Ngatai Road to Bureta Road during this time. Properties, businesses and the golf course will remain accessible via detours. Bus services normally using Bureta Road past the shops will detour via Vale Street, with a temporary stop in place. Pedestrian and cycle access will be maintained, including temporary crossings on Ngatai Road and a temporary footpath through Bureta Park.

Detours will operate as follows:

  • Light vehicles: Ngatai Road – Short Street – Freyberg Short – Landscape Road – Vale Street – Bureta Road
  • Heavy vehicles: From east: Vale Street – Bureta Road. From west: Ngatai Road – Ōtūmoetai Road – Grange Road – Vale St – Bureta Road 

This stage will include construction of a new shared path, kerb and channel, drainage upgrades, installation of streetlights and signal poles for the pedestrian crossing, and landscaping works.

With a history of multiple crashes, and ranked as Tauranga’s number one high-risk intersection, this project is a vital step toward protecting everyone who uses this busy route — drivers, cyclists, and pedestrians.

Since 2019, there have been 19 reported crashes at this intersection — eight with injuries and 11 due to failure to give way or stop.

Community consultation

During community consultation for the Ōtūmoetai Spatial Plan, residents called for stronger safety measures at this location.

Although the wider Ōtūmoetai Area B safety programme did not receive NZTA funding, this intersection was prioritised by council due to its critical safety concerns and received separate funding approval.

What’s changing

A roundabout with crossings will replace the current intersection to slow down traffic and improve safety around the intersection. Traffic modelling showed that a signalised intersection would cause major congestion on Ngatai Road during peak hours. A roundabout was chosen as the best option to enhance safety while maintaining smooth traffic flow.

Work on the Ngatai/Bureta Road intersection safety improvements started the week beginning Monday, April 20 and is expected to take four months to complete, weather permitting.

  • A roundabout with new footpaths will replace the current intersection.
  • Two shared crossings (for pedestrians and cyclists) on Bureta Road, one on either side of the roundabout.
  • A signalised pedestrian crossing on Ngatai Road (near TyreMaster and Superior Automotive). The existing crossing will be removed.
  • A pedestrian refuge island on Ngatai Road (near the golf club).
  • Wider footpaths where possible to accommodate the growing number of pedestrians and cyclists and improve accessibility.
  • Cycle on/off ramps on all approaches to the roundabout.
  • New kerb from the Ngatai/Bureta Road intersection to the Ngatai Road/Chapel Street intersection.

Some parking changes are needed to safely deliver the roundabout, improve visibility, and provide safer crossings for people walking and cycling. Importantly, some of these parking spaces would need to be removed even without the shared crossing, due to the roundabout layout and safety requirements.

Overall, 14 existing parking spaces will be removed, with new parking provided nearby to help offset this where possible.

Where parking will be removed

  • Bureta Road (outside the golf club):
    Five parking spaces will be removed to accommodate the roundabout layout and a new shared crossing.
  • Bureta Road (outside the superette and fish and chip shop):
    Four parking spaces will be removed to allow safe vehicle reversing, reduce conflicts near the roundabout, and accommodate a new pedestrian crossing. Nine parking spaces will remain outside the shops.
  • Ngatai Road (towards Matua, before the intersection):
    Four parking spaces will be removed to make room for a new signalised pedestrian crossing.
  • Ngatai Road (towards the city, after Superior Automotive):
    One parking space will be removed to accommodate a new cycle ramp.

Where parking will be added or improved

  • Bureta Park (near the golf club):
    Six new P60 parking spaces will be added within the park.
  • Outside the shops on Bureta Road:
    To support customer turnover, there will be five P15 and four P60 parking spaces
  • Bus stop changes:
    The bus stop opposite the shops and outside Bureta Park will be relocated further south. This allows for two new P60 parking spaces to be added closer to the shops, while two spaces further down the road will be removed to accommodate the relocated bus stop.

Ngatai/Bureta map
Ngatai/Bureta Road intersection safety improvements – concept design. (429kb pdf)

Traffic volumes

Weekday average of vehicle movements along Ngatai Road (between Bureta Road and Crescent Road) in both directions: 13,015

Weekday average of vehicle movements along Ngatai Road (between Bureta Road and Chapel Street) in both directions: 11,825

Daily average of pedestrians and cyclists crossing Ngatai Road at the existing crossing: 160

Key dates

  • Design plans shared with the community

    October 2025
  • Final design confirmed

    March 2026
  • Construction

    Late April 2026 to Late August 2026
  • Project completion

    September 2026

Who's listening

Transport Team
Tauranga City Council

transportcomms@tauranga.govt.nz 
07 577 7000

Sign up to stay informed

If you want to stay updated, sign up for our Kōrero mai - Let’s talk Tauranga newsletter.

Sign up to stay informed

Neighbourhoods

Find out what other projects are happening in Matua-Ōtūmoetai.

Matua-Ōtūmoetai projects

 

Tauranga City Council, Private Bag 12022, Tauranga, 3143, New Zealand |Terms of use|Privacy statement

Back To Top