Oropi Road sinkhole update #2

This afternoon from 12.30pm onwards, Tauranga City Council is closing Oropi Road between Cheyne Road and the Oropi Stream Bridge for repair works to reopen both lanes. The road is expected to reopen by 4pm today.

Detour signage is in place to redirect vehicles. Cyclists and pedestrians will continue to have access.

As soon as the repair works are finished, the temporary traffic management will be removed. A temporary 50kph speed limit will be in place.

Last night the sinkhole near the Oropi Stream Bridge reopened. The likely cause for the reopening of the sinkhole was a tear in the protective fabric, which combined with the high tide, heavy rainfall and increased streamflow, allowed further erosion.

The consequence was the creation of a new cavity under the road. Once we were notified, the affected part of the road was restricted to a single lane under temporary traffic management, which included a reduction in speed limit from 80kph to 30kph.

Engineers will continue to monitor and inspect the road on a weekly basis and work with the Council to find a permanent solution.

Posted: Sep 5, 2019,

Other ways to get involved

Tauranga is your city. We're working to make it even better.

Tauranga City Council, Private Bag 12022, Tauranga, 3143, New Zealand |Terms of use|Privacy statement

Back To Top